Restoration: Renovation of prestigious structure, East Devon
China Tower, East Devon.
Complete refurbishment & up-grading of a Grade II derelict building.
Restoration works included:
- Installation of new 3 phase electrical mains
- Installation of new electrics and plumbing & heating system – supplied from an air source heat pump system
- Roofs re-covered in lead, including all associated carpentry works
- Lime rendering works internal & external
- Insulation upgrade to floors
- Excavation of existing ground floor and upgrade of floor construction
- Installation of new shower room
- Stone masonry, moulding works and render repairs
- All new bespoke joinery carried out by our in-house joinery department
- Installation of new access road
Case Summary
- Client: Devon Estate and Landmark Trust
- Architect: Jonathan Rhind Architects Ltd
- Value: £275,000
- Procurement: Single Stage Tender
- Programme: 24 weeks
- Completed: 2014